Capral Aluminium
Aluminium Remelt Facility Upgrade
On-site round-the-clock presence allowed GW Engineers to reduce a construction program for Capral Aluminium Limited from six weeks to three.
GW Engineers was engaged to assist with the planning, design and project management of the civil works consisting of the foundations for three homogenising furnaces and cooling chambers scrap storage corrals and replacement of three 25 cubic metre capacity clam shell scrap buckets which load the re-melt furnace.